1. |
The foundation of a building or structure transfers the dead and live loads of the superstructure to soil that has enough bearing capacity to support the structure in a permanent, stable position. |
|
|
True |
|
|
False |
2. |
Foundation walls without footing is usually is used for: |
|
|
Light weight buildings |
|
|
Bridges |
|
|
Homes |
|
|
Office buildings |
3. |
Soil conditions may change over a period of time and introduce maintenance and repair problems even in initially well- designed foundations. |
|
|
True |
|
|
Fault |
4. |
Which of the followings would be considered as common causes of foundation movement. |
|
|
Settlement and differential settlement of the soil caused by inadequate compaction of the soil |
|
|
Improper sizing of the footings |
|
|
Over loading the structure |
|
|
Excessive ground water which reduces the bearing capacity of soil |
|
|
Inadequate soil cover which fails to protect against frost heaving |
|
|
Adjacent excavation that allows unprotected bearing soil to shift from under foundations to the excavated area. |
|
|
All of the above) |
5. |
Localized foundation displacement may show upin: |
|
|
Cracked walls |
|
|
Damaged framings and connections |
|
|
Sloping floors |
|
|
Sticking doors |
|
|
Leakage through a displaced roof |
|
|
All of the above |
6. |
The minimum practical thickness for a medium duty slab is: |
|
|
4 inches |
|
|
6 inches |
|
|
8 inches |
7. |
In the process called curing the concrete should be kept from drying out for at least |
|
|
5 days |
|
|
15 days |
|
|
30 days |
|
|
60 days |
8. |
The structural component of a frame building should be strong enough and sufficiently rigid to transfer dead and live loads to the building foundations without excessive deflection or side sway. |
|
|
Ture |
|
|
False |
9. |
Dead loads are those that result from the weight of the structure and live loads are those induced by external forces such as wind, earthquake, snow, inhabitants, furniture, equipment, or impact. |
|
|
True |
|
|
False |
10. |
The fundamental principals of framing falls into two categories. Balloon frame and platform frame. |
|
|
Ture |
|
|
False |
11. |
The balloon frame is light, economical, and simple to construct. |
|
|
True |
|
|
False |
12. |
The balloon frame is more rigid and heavier than the platform frame. |
|
|
True |
|
|
False |
13. |
Post and columns are vertical members which transmit loads directly to the foundations. |
|
|
True |
|
|
False |
14. |
Post and columns below grade or in contact with earth must be treated with a preservative to resist decay and termite damage. |
|
|
True |
|
|
False |
15. |
Beam or joists, which have failed in bending but have sound wood surrounding the failure, may be repaired by fastening adjacent pieces (scabs) to the side of the failed member. |
|
|
True |
|
|
False |
16. |
There are many methods which can be used to reinforce girders, beams and joists. The selection of the proper methods should be determined by the loads to be carried, the costs, clearances, and accessibility. |
|
|
True |
|
|
False |
17. |
Fire stops are obstructions deliberately placed in concealed air spaces to block passage of hot gases and flames from on area to another. |
|
|
True |
|
|
False |
18. |
Failure of wall framing is usually related more to major structural faults elsewhere in the construction than to defects in the framing itself. |
|
|
True |
|
|
False |
19. |
Warped studs can frequently be returned to original alignment with additional bridging. Headers, lintels, and sills can be returned to horizontal position by proper shimming. |
|
|
True |
|
|
False |
20. |
Any major structural repairs or replacements such as the latter should not be undertaken in load bearing walls without first removing the loads from the wall under repair by adequate shoring and jacking. |
|
|
True |
|
|
False |
|