1. |
What type of wood was used for the diagonal bracing member? |
|
|
CMU blocks |
|
|
2×4 |
|
|
Southern Yellow Pine (SYP) OSHA scaffold plank |
2. |
What was required by the contract documents for quality assurance during construction? |
|
|
Independent testing company to perform site inspections and testing |
|
|
Architect to perform periodic visual observations of the structure after construction. |
|
|
Contractor to perform site inspections and testing |
3. |
How many employees were killed during the collapse of the east wall? |
|
|
one |
|
|
Four |
|
|
two |
|
|
three |
4. |
One of the purpose of structural analysis was to determine whether the installation of the temporary bracings was properly done in accord with the applicable industry standards.
|
|
|
True |
|
|
False |
5. |
What was the maximum spacing of the control joints specified by the architect for the CMU walls?
|
|
|
40" on center |
|
|
25’ on center |
|
|
6 bracings |
6. |
How could the incident have been prevented? |
|
|
By reducing the lateral wind load on the wall. |
|
|
By placing the rebar dowels correctly in the footing at the center of the wall. |
|
|
By using stronger materials in the construction of the wall. |
7. |
How many exterior braces were removed from the east wall prior to the collapse? |
|
|
All three |
|
|
Two |
|
|
None |
8. |
What was the cause of the incident in the CMU wall? |
|
|
The masonry did not gain adequate strength in 15 days. |
|
|
The overturning moment due to lateral wind load was higher than the resisting moment induced by the self-weight of the CMU wall. |
|
|
The dowel reinforcements were misplaced to the center of the wall. |
9. |
What type of detail is shown in this figure?
 |
|
|
Beam column joint detail |
|
|
Control joint detail |
|
|
Bracing detail |
|
|
All of the above |
10. |
What caused the collapse of the east wall? |
|
|
Human error |
|
|
Strong winds |
|
|
Earthquake |
|
|
Heavy rain |
|