Member Login
New User Registration
Home
All PDH Courses
Shop By Price
$3 PDH
$6 PDH
$12 PDH
$15 PDH
Shop By Subject
ADA Accessible Design
Architects
Business Skills Courses
Civil Engineering
Contractors
Electrical Engineering
Environmental Engineering
Ethics & Laws Courses
Florida Professional Engineers
Geologists
Green Building
Home & Building Inspectors
Landscape Architects
Land Surveyors
Mechanical Engineering
Oil & Gas and Petrochemical Engineering
Structural Engineering
State Requirements
About Us
Contact Us
Member Login
New User Registration
Member Login
New User Registration
Repair of Rigid Pavement Using Epoxy - Quiz
Quiz Question
1.
The epoxy resin is the resin component of thermosetting polymer which contains epoxy groups principally responsible for its polymerization.
True
False
2.
Generally pavement repairs with epoxy materials shall not be initiated unless the air and pavement temperatures are above 40 degrees F and rising.
True
False
3.
Epoxy resin type I, is used to bond hardened concrete and other materials to hardened concrete. It is used for cementing dowels in drilled and preformed holes and for pressure grouting of nonworking cracks.
True
False
4.
Epoxy resin type II, is used to bond freshly mixed Portland cement concrete (PCC) to hardened PCC.
True
False
5.
Epoxy resin type III, is used to bond skid-resistance materials to hardened concrete, and as a binder in epoxy resin mortars or epoxy resin concretes for repairing spalls and for filling non-working joints.
True
False
6.
Figure 1 shows :
Different methods of applying the resin epoxy
Approved methods for repair of uncontrolled cracks and spalls in rigid pavements.
Crack growth in concrete
7.
In fig. 1 Condition 7, if the cracks are tight and not working we need to:
Remove and replace full slab
No repair required
8.
Because of the nature of the hardened epoxy resin systems, all tools and equipment need not be thoroughly cleaned before the epoxy materials set.
True
False
9.
The viscosity of the two components of an epoxy resin increases as temperatures decrease.
True
False
10.
In the preparation of epoxy resin concretes and mortars, aggregates should be dry and conditioned to a temperature of_______________________.
70 to 85 degrees F
90 to 125 degrees F
11.
Figure 3 shows :
Placement of joint filler sheet to maintain active crack through area to be patched.
Breaking and crushing the old pavement before removal
12.
Figure 4 shows:
Placing fillers in the concrete before concrete curing
Finishing a patch containing an active crack